How Base NPI Forecast & Final NPI Forecast are calculated

Created by Shyam Sayana, Modified on Thu, 26 Nov at 6:26 AM by Shyam Sayana

TABLE OF CONTENTS


Overview

When you create an NPI plan, the application first builds a Base NPI Forecast by blending the history of your like products. You then choose how that forecast is shaped over time. This article walks through five real examples, step by step, using the same plan each time so you can compare them:

ExampleRamp-up curveBusiness volume estimate
1NoneNot applicable
2S-CurveNo
3S-CurveYes, 1,500 units
4From another product (reference product)No
5From another product (reference product)Yes, 1,500 units

For the screen itself, see How to create NPI plan?. For how the curves work, see What is S-Curve (Logistic curve) in the NPI Plan? and NPI Ramp-Up Curve Generation Using Another Product.


The starting point for all examples

SettingValue
New product (NPI product)PRD005, Cardinal Hazelnut Praline Bar, 90g
NPI periodJan 2026 to Jun 2026 (6 months)
NPI Input MeasureShipped Quantity
Like product 1PRD006, Cardinal White Chocolate Bar, 100g. Weight 60%, Start Jul 2025
Like product 2PRD008, Cardinal Orange Zest Dark Chocolate, 100g. Weight 40%, Start Jul 2025

The weights add up to 100%. For each like product, the End is filled in automatically as Dec 2025, so six months of history are copied: Jul 2025 to Dec 2025.


How the Base NPI Forecast is built

The application lines up the like products' history by position. Month 1 of your plan (Jan 2026) uses the first month of each like product's history (Jul 2025), month 2 uses the second month, and so on. For each month it multiplies each like product's sales by its weight and adds them up.

Plan monthLike product 1 sales (PRD006)Like product 2 sales (PRD008)CalculationBase NPI Forecast
Jan 2026 (from Jul 2025)2602080.60 × 260 + 0.40 × 208 = 156 + 83.2239
Feb 2026 (from Aug 2025)2622770.60 × 262 + 0.40 × 277 = 157.2 + 110.8268
Mar 2026 (from Sep 2025)1712140.60 × 171 + 0.40 × 214 = 102.6 + 85.6188
Apr 2026 (from Oct 2025)4294440.60 × 429 + 0.40 × 444 = 257.4 + 177.6435
May 2026 (from Nov 2025)2675870.60 × 267 + 0.40 × 587 = 160.2 + 234.8395
Jun 2026 (from Dec 2025)3626030.60 × 362 + 0.40 × 603 = 217.2 + 241.2458

The six months add up to about 1,984 units. This is the Base NPI Forecast, and it is the same in all five examples.


Example 1: No ramp-up curve

What you do

  1. Fill in the plan as above.
  2. In the Ramp up curve section, leave None selected.
  3. Click Save Plan, then run the plan.

What happens. No curve is applied. The Ramp-Up Curve row shows 100% in every month, and the Final NPI Forecast is the same as the Base NPI Forecast.

JanFebMarAprMayJunTotal
Base NPI Forecast2392681884353954581,983
Ramp-Up Curve100%100%100%100%100%100%
Final NPI Forecast2392681884353954581,983

When to use it. Use this when the like products' own pattern is exactly how you expect the new product to behave, or when you have no view on how fast sales will build.


Example 2: S-Curve without a business volume estimate

Here you expect sales to start slowly and build up, but you have no target for the total.

What you do

  1. In the Ramp up curve section, choose From standard curve.
  2. Set Curve type to S-Curve.
  3. Leave the sliders at their starting values: Growth starts (k) = 1, Growth rate (a) = 1, and market share from 0% to 100%.
  4. Leave the ramp up start and end as they are (Jan 2026 to Jun 2026), so the curve covers the whole NPI period.
  5. Leave Business volume estimate (units) empty.
  6. Click Save Plan, then run the plan.

What happens, step by step

Step 1: The S-Curve. The curve gives each of the six months a percentage. It starts low, rises quickly in the middle, and flattens near the top:

JanFebMarAprMayJun
Ramp-Up Curve7.6%18.2%37.8%62.3%81.8%92.4%

Step 2: Apply the curve to the Base NPI Forecast. Each month's Base forecast is multiplied by its curve percentage.

JanFebMarAprMayJunTotal
Base NPI Forecast239.2268.0188.2435.0395.0458.41,983.8
× Ramp-Up Curve× 0.0759× 0.1824× 0.3775× 0.6225× 0.8176× 0.9241
= Base × curve18.248.971.0270.8323.0423.61,155.4

Step 3: Keep the total the same. The curve only changes when the sales happen, not how many there are. The six months now total 1,155.4, so the application scales them back up to the original total of 1,983.8. The scale factor is 1,983.8 ÷ 1,155.4 = 1.7169.

JanFebMarAprMayJunTotal
Ramp-Up Curve7.6%18.2%37.8%62.3%81.8%92.4%
Final NPI Forecast31841224655547271,983

Compared with Example 1, the sales are pushed later, with less in the early months and more in the later months. The total is unchanged.


Example 3: S-Curve with a business volume estimate

This is the same as Example 2, but the sales team expects 1,500 units in the six months, and you want the forecast to add up to that.

What you do. Do the same as in Example 2, and also type 1500 in Business volume estimate (units). Then save and run the plan.

What happens, step by step. Steps 1 to 3 are exactly as in Example 2. They give the forecast after the curve: 31.2, 83.9, 122.0, 464.9, 554.5 and 727.3, a total of 1,983.8.

Step 4: Apply the business volume estimate. You entered 1,500 units, so the application scales the whole forecast so that its total is exactly 1,500. The scale factor is 1,500 ÷ 1,983.8 = 0.7561. The estimate can be lower or higher than the Base total. Here it is lower, so every month is reduced by the same share. The monthly numbers are rounded to whole units so that the total is exactly 1,500.

JanFebMarAprMayJunTotal
Forecast after the curve (Example 2)31.283.9122.0464.9554.5727.31,983.8
× 0.756123.663.592.2351.5419.3549.91,500.0
Final NPI Forecast (whole units)2463923524195501,500

What to remember.

  • The curve decides the shape: slow at the start, faster later.
  • The business volume estimate decides the total.


Example 4: Reference product without a business volume estimate

Here you don't use a ready-made curve. You tell the application to copy how an existing product's sales were spread across the same months.

What you do

  1. In the Ramp up curve section, choose From other product.
  2. In Reference product, choose PRD042, Sunrise Black Tea Bags, 100-count.
  3. Leave the business volume estimate empty, and leave the ramp up window as it is (Jan 2026 to Jun 2026).
  4. Click Save Plan, then run the plan.

What happens, step by step

Step 1: Read the reference product's sales. The application reads the reference product's sales (using the NPI Input Measure, Shipped Quantity) in the same calendar months as your ramp up window, Jan 2026 to Jun 2026:

Jan 2026Feb 2026Mar 2026Apr 2026May 2026Jun 2026
Reference product sales7621,0921,1661,2821,3251,561

Step 2: Turn the sales into a curve. The highest month, June at 1,561, becomes 100%. Every other month is shown as a share of it:

JanFebMarAprMayJun
Sales ÷ 1,561 = Ramp-Up Curve48.8%70.0%74.7%82.1%84.9%100%

Step 3: Apply the curve to the Base NPI Forecast.

JanFebMarAprMayJunTotal
Base NPI Forecast239.2268.0188.2435.0395.0458.41,983.8
× Ramp-Up Curve× 0.4881× 0.6996× 0.7470× 0.8213× 0.8488× 1.0000
= Base × curve116.8187.5140.6357.3335.3458.41,595.8

Step 4: Keep the total the same. As in Example 2, the total goes back to the Base total. The scale factor is 1,983.8 ÷ 1,595.8 = 1.2432.

JanFebMarAprMayJunTotal
Final NPI Forecast1452331754444175701,984

The shape now follows the reference product: a lower start that builds up steadily to June.

Choosing a good reference product

  • Pick a product whose launch or growth pattern is what you expect for the new product.
  • The reference product must have sales in the ramp up window's months. If it has none, the application cannot build a shape. It then applies no curve and shows a warning on the results.


Example 5: Reference product with a business volume estimate

This is the same as Example 4, but the sales team expects 1,500 units in the six months.

What you do. Do the same as in Example 4, and also type 1500 in Business volume estimate (units). Then save and run the plan.

What happens, step by step. Steps 1 to 4 are exactly as in Example 4. They give the forecast after the curve: 145.1, 233.1, 174.8, 444.1, 416.8 and 569.9, a total of 1,983.8.

Step 5: Apply the business volume estimate. The application scales the whole forecast so that its total is exactly 1,500. The scale factor is 1,500 ÷ 1,983.8 = 0.7561, the same as in Example 3, because the total before the estimate is the same. The monthly numbers are rounded to whole units so that the total is exactly 1,500.

JanFebMarAprMayJunTotal
Forecast after the curve (Example 4)145.1233.1174.8444.1416.8569.91,983.8
× 0.7561109.7176.2132.1335.8315.2430.91,500.0
Final NPI Forecast (whole units)1101761323363154311,500

What to remember.

  • The reference product decides the shape.
  • The business volume estimate decides the total.
  • The estimate works the same way with a reference product as it does with an S-Curve.


Comparing the five results

JanFebMarAprMayJunTotal
Base NPI Forecast2392681884353954581,983
Example 1: No ramp-up curve2392681884353954581,983
Example 2: S-Curve, no business volume estimate31841224655547271,983
Example 3: S-Curve, business volume estimate 1,5002463923524195501,500
Example 4: Reference product, no business volume estimate1452331754444175701,984
Example 5: Reference product, business volume estimate 1,5001101761323363154311,500

The totals differ by 1 in places only because each month is rounded to whole units. The five results show:

  • Without a curve, the forecast follows the like products exactly.
  • A curve (Examples 2 and 4) changes only the timing. The total stays the same.
  • A business volume estimate (Examples 3 and 5) changes only the total. Examples 2 and 3 have the same shape, and so do Examples 4 and 5. Each is just scaled down to 1,500.
  • The S-Curve holds sales back in the early months, while the reference product starts higher and builds up gradually.

Which one should I use?

If…Use
You have no view on how sales will build, or the like products are already a good matchNone (Example 1)
You expect a classic slow start, then faster growth, then levelling offFrom standard curve, S-Curve (Examples 2 and 3)
An existing product launched in a way you expect to repeatFrom other product (Examples 4 and 5)
The business has a unit target for the periodAdd a business volume estimate to either curve (Examples 3 and 5)

What should I watch out for?

  • A curve does not change the total. It only moves the sales between months. Only the business volume estimate changes the total.
  • A business volume estimate scales the whole forecast. It applies to every month of the NPI period, whatever the like products showed, and it works the same with an S-Curve or a reference product.
  • The reference product's shape comes from the same calendar months as your ramp up window, not from the months after its own launch. Make sure it has sales in those months.
  • You can narrow the ramp up window. Months outside the window follow the Base NPI Forecast with no curve.
  • After you change a curve or estimate, save the plan and run it again to see the new results. See How do you edit and re-run the NPI plan?.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article